Sunday, March 15, 2015

16 mar 15

Tim
Production Calendar says:
animated:
sh03
sh08
sh10
sh20

did:
sh04

• Need printable production still based on Annecy specs

Mee
Production Calendar says:
animated:
sh 09, 10, 11, 12, 13, 14 keyed

• Need printable production still based on Annecy specs

Chris
Production Calendar says:
doesn't indicate what work was to be done.

*production calendar does not clearly indicate total number of shots, or what work will be done for today's class.
• Add description to influences: how do they inform your piece?
• Synopsis is minimal and contains an obvious grammatical error. please fix.
• Influences are just links: add description of how they impact your piece, and make the links into clickable words instead of URLs.
• Correct spelling of the word "Production Still": attention to detail makes you look good. Inattention to detail makes you look the opposite.
• Make production calendar page link go to another tab rather than replacing your blog.
• Shot list: mark shots as "easy," "medium," or "difficult," and tally up the number of days it will take to animate them.
• If you have revised your animatic so that there are fewer shots, this should be reflected in your shot list/production calendar
• Add dates to the production calendar all the way to the end.
• Need printable production still based on Annecy specs


Meghan
Production Calendar says:
animated:
DURING BREAK A: S16, Title, Credits

James
Production Calendar says:
4 Shots rough animated *Please make the Production Calendar functional, and indicate specific shots and dates.

Done: ???

• Need printable production still based on Annecy specs
• Put finished shots together to start building a new animatic

Cynthia
Production Calendar says:
sh25
sh26
sh27
sh28
sh29
sh30
sh31
sh32

Done: all shots marked as "in-progress"

Andrew
Production Calendar says:
• preliminary backgrounds 3, 4, 5 done. sh07, 08 animated.
• sh09, 10, 11 animated.
• sh12, 13, 15, 16 animated.

Done: None.

• Add dates for final backgrounds in Shot List & Production Calendar
• add festival program-style synopsis to "About" page

Andre
Production Calendar says:
*no work indicated

• Fill in missing dates in your Production Calendar

Ra'shon
84 seconds animated (no shot list or production calendar on blog)

• Production Calendar & Shot List?
• Rework story beginning and end so they reflect the cliché upon which the story is based.
• Rapidly passing the point of no return, here. See me in class.

Posted 2 layouts for BG's.

Production Calendar says:
• shot03back 
• shot4back 
• shot05back

Greg
Production Calendar says:
living room.

Done: part of living room.

• Add seconds to each sequence defined in Production Calendar (e.g. "Commercial, 24 sec.")
• Embed movie into "animatic" page.
• Need printable production still based on Annecy specs

Marc
Production Calendar says:
84 seconds animated & colored.

• Shot 24
• Shot 25
• Shot 28

• "ending sequence"

Sunday, March 1, 2015

Work Due for March 2nd, Week 6

*Note: missing production stills and incomplete Production Calendars/Shot Lists bring your grade down each week they remain unfinished. Grades are available on Digication.

Tim
Production Calendar says:
animated:
sh07
sh15
sh14
sh16
sh05 animated (from last week)

• Does the Production Calendar include all of your shots? 
• Total number of days of animation (easy, medium, difficult) still needs to be added up. How many backgrounds, total?
• Need printable production still based on Annecy specs

Notes: one shot, unidentified, posted to blog, 1 second duration.

Mee
Production Calendar says:
animated:
sh09
sh10
sh11
sh14
sh15

sh04, 05, 06, 07, 08 posted. Post other finished shots. Revise Shot List/Production Calendar as needed.
• Questions: re-size multiple images in Toon Boom; coloring in Toon Boom
• Need printable production still based on Annecy specs

Notes: no work posted.


Chris
Production Calendar says:
animated:
sh14
sh15
sh16
sh17
sh18

• What's the difference between the red and the strike-throughs on your production calendar? It's not clear. Please fix.
• Add description to influences: how do they inform your piece?
• Synopsis is minimal and contains an obvious grammatical error. please fix.
• Influences are just links: add description of how they impact your piece, and make the links into clickable words instead of URLs.
• Correct spelling of the word "Production Still": attention to detail makes you look good. Inattention to detail makes you look the opposite.
• Make production calendar page link go to another tab rather than replacing your blog.
• Shot list: mark shots as "easy," "medium," or "difficult," and tally up the number of days it will take to animate them.
• If you have revised your animatic so that there are fewer shots, this should be reflected in your shot list/production calendar
• Add dates to the production calendar all the way to the end.
• Need printable production still based on Annecy specs

Notes: 60 seconds of rough animation posted. Good progress with animation this week, but cannot tell what shots are what until shot list and production calendar are updated. See notes, above and make sure to make revisions.

Meghan
Production Calendar says:
animated:
sh21
sh22
sh23

Notes: Done. Make note of which shots have been posted and update Shot List. Good progress.

James
Production Calendar says:
3 Shots rough animated *Please indicate which shots in the Production Calendar. (sh04, sh05, sh06 indicated only in Shot List, which is not chronological)

• Need printable production still based on Annecy specs
• Put finished shots together to start building a new animatic

Notes: Shot "Chair get up" posted (sh04?).

Cynthia
Production Calendar says:
sh05
sh06
sh07
sh08
sh09
sh10
sh11
sh12
sh13
sh14
sh15

• Embed video into blog post rather than just using the link to make it one step for the viewer to see
• ps - I like your "Apple" animation from Object Animation class: nice acting, rich color and lighting

Notes: Production Calendar says sh05, 06, 07, 08, 09, 10, 11, animated, sh12, 13, 14, 15 in progress. Please note which shots are done on post.

Andrew
Production Calendar says:
preliminary bg sh03
preliminary bg sh04
preliminary bg sh05
sh07 animated
sh08 animated

• Synchronize production calendar and shot list.
• Key animation posted for sh06; sh05 zoom
• Add dates for final backgrounds in Shot List & Production Calendar
• add festival program-style synopsis to "About" page

Notes: bg03, 04, 05 posted. Keys for sh05, 06, 07 posted.

Andre
Production Calendar says:
shot07 bg
shot08 bg

Shot List says:
sh07 animated

• Fill in missing dates in your Production Calendar

Notes: no worked posted to blog.

Ra'shon
60 seconds animated (no shot list or production calendar on blog)

• Production Calendar & Shot List?
• Rework story beginning and end so they reflect the cliché upon which the story is based.
• Rapidly passing the point of no return, here. See me in class.

Notes: no work posted to blog.

Greg
Production Calendar says:
audio editing/timing finalized.

• Add seconds to each sequence defined in Production Calendar (e.g. "Commercial, 24 sec.")
• Embed movie into "animatic" page.
• Need printable production still based on Annecy specs

Notes: no work posted to blog.

Marc
Production Calendar says:
60 seconds animated & colored.

• Revise Shot List dates so they reflect a regular working pattern.
• Synch Production Calendar to revised Shot List.

Notes: roughly 50 seconds posted to blog.